IMR案例-伊莱克斯 空气净化器

目标Objective

从产品研发到产品实现只有30天,属于快速研发产品,最后量产时间提前到第22天。It only takes 30 days from product research and development to product realization, which is a rapid product research and development. Finally, the mass production time is advanced to the 22nd day.

任务Tasks

15
研发
20
模具制造
20
注塑成型
15
箔膜研发
5
材料检验
7
产品改良
综述Overview

03/2020  

苏州Suzhou & 东莞Dongguan, China

开始研发时间  In March, it began to enter the mold making process


04/2020

China

产品发布前成功完成      We successfully finalised this project on time.


05/2020

China

本次批量7000套成功完成,产品全部投放欧美市场       This batch of 7000 sets has been successfully completed, and all the products have been put into European and American markets